Dehradun : Whereas rampant corruption, nepotism and
complete lack of governance have been the bane of Uttarakhand, because
of which the ambitions and aspirations of the people continue to remain a
distant dream even 12 years after achieving statehood, there seems to
be no soft corner of the centre also towards the developmental
activities of this small mountain state.
Though it is mandatory to get forest clearance from the union
ministry of environment and forests for projects in which forest land is
involved, but the very fact that over 70 per cent of Uttarakhand comes
under forests, has not been taken into consideration while giving
clearance for even making roads to provide much needed connectivity to
thousands of villages that are languishing.
Senior politicians cutting across party lines, are unanimous of the
view that despite various proposals sent to the centre for clearance,
most of them have been languishing there, some since when the state came
into being. They have not even taken into consideration the fact that
the state it still in its infancy and needs the roads for development,
they lamented.
From 2002 to 2011, the Uttarakhand government has sent proposals for
524 roads to be constructed in various parts of the state, most of them
in the hilly tracts which have a crying need for connectivity. The roads
total 3804.73 kms and a sum of about Rs 1300 crores has been sanctioned
for them, but forest clearance from the union ministry of environment
and forests is still awaited.
What is perturbing is the fact, that even the bureaucracy and for
that matter the state government conveniently pass on the buck to the
forest department for the stagnancy in the developmental projects.
Though in the past the excuse was that there is a BJP government in the
state and the Congress government at the centre, because of which
clearances are not given, but now there are Congress governments both at
the centre and the state and as such efforts should be made to get the
clearances.
In fact, it is not only in the case of roads, various other
developmental projects, which could affect the economy and development
of the higher reaches of the state have been pending for years now for
want of forest clearance. What is adding to the woes of this small
mountain state, that with the passing of time the cost of the projects
is also increasing and the amount sanctioned for them, may actually not
be sufficient for their completion.
It was reliably gathered that the cost of sanctioned roads may have
already increased from the Rs 1300 crores to about Rs 2100 crores, which
could put some of the sanctioned roads into jeopardy for want of funds
for completing them.